MUMBAI: Larsen & Toubro Ltd. (L&T) has been awarded a Rs 403 crore
contract by Nuclear Power Corporation of India Ltd. (NPC) and a Rs 176 crore
order from Gujarat Industrial Development Corporation (GIDC). ECC, the
Construction Division of L&T, will be executing the project for NPC, which
involves execution of their turnkey electrical contract at 500 MWe Tarapur Units
3 & 4 in Maharashtra. The project when implemented would become the first
500 MWe nuclear power plant in the country.
The scope of work involves design, manufacture, supply, erection, testing and
commissioning of the entire electrical equipment and ancillaries required for
both the Units. This includes installation of 400 kV and 220 kV gas insulated
switchgear, hotline washing system, generator circuit breakers, transformers, DG
sets and isolated bus ducts on a total turnkey basis. Most of the critical
equipment will be imported. ECC is expected to complete the work by June 2005.
The other project with GIDC, Bharuch has also awarded Rs 176 crores turnkey
contract to ECC, for setting up facilities for disposal of treated effluents
from Vilayat in GIDC Industrial Estate to the sea in the Gulf of Khambhat. This
is a first of its kind project in India and a major step towards environment
protection and sustaining bio-diversity.
The work involves design, supply, laying, jointing and commissioning 55.5 km
pipeline conveying system - both on shore and offshore including construction of
pumping stations with electro-mechanical services and cathodic protection on a
total turnkey basis to be completed in a stringent time frame of 18 months.